DNi has completed Phase One and Phase Two of its commercialisation programme consisting of bench scale batch and semicontinuous test work. DNi has invested ~A$10M in the programme since late 2006.

The Deliverables Include

  • Three simple alternative flowsheet options, with no red flags
  • Input data for Pre-Feasibility Study Two (PFS 2) design criteria
  • Metsim™ process models to allow economic estimates
  • PFS2 delivered by Aker Solutions in June 2009
  • Sufficient information to start Phase 3, the Demonstration Plant phase
   